Office of Regulatory Assistance Spotlight SeriesSearch | Site Map

Transportation Permit Efficiency and Accountability Committee

HomeAbout TPEACProductsPractitioners' CornerNext Steps

Lessons Learned

As with any process aiming to foster collaboration between a diverse group of stakeholders, the TPEAC experience was not without its challenges.  Participants' individual perceptions varied, but there were several commonly identified issues that can be captured in general lessons about the TPEAC process and its products.  It is hoped that the following "Lessons Learned", in combination with the "nuts-and-bolts" advice captured in Practitioners Corner, will bring the benefit of hindsight to future collaborative efforts and to the implementation of TPEAC's products.

Click on an item below to read more about the lesson and link to advice and resources:

TPEAC Process Lessons Learned

TPEAC Process Lessons Learned

Clearly understanding and defining the problem(s) are crucial to developing an effective approach.

When developing a collaborative approach, a clear understanding and definition of the problem is essential if progress is to be made.  TPEAC's enacting legislation specified the purpose and general intended outcomes of the Committee, and within the first few meetings specific performance measure targets were defined (see Next Steps - Performance Measures).  However, TPEAC brought together a diverse group of stakeholders to address a complex and somewhat divisive issue.  Accordingly, members did not come to the table with a unified perception of the need, goals, and methods for "streamlining" the permitting process.  In the absence of a shared vision, the Committee may have benefited from an initial period of data collection and discussion to define the problem and outline the objectives.

Additional Information:

Back to top.

Building effective relationships is both the challenge and the reward of the collaborative process.

TPEAC required a new, higher level of interested party cooperation that had not been occurring.  Agencies and key interests that had operated independently in the past were required to work together to accomplish the goals of permit streamlining with greater environmental benefits.  Participants brought diverse agendas and expectations to the table.  The TPEAC experience highlights that it takes time to orient participants to the objectives and obligations of fellow committee members and that this orientation appears to be crucial to the establishment of credibility and trust among parties.

Quite a bit of time was spent at the beginning of the process sharing perspectives and educating everyone on transportation project development and permit processes. Certain participants felt that the initial emphasis on process was unproductive, while others felt it was important to the establishment of trust and credibility.

Additional Information:

Back to top.

Appropriate participation at all phases in the process is critical to the overall effectiveness of a group's efforts.

In TPEAC, it became apparent that missing key participants can negatively impact the overall effectiveness of the efforts of the committee and its subcommittees.  For some subcommittees, key participants missed the beginning of the process.   As a result they missed the conversations establishing the shared understanding and the identification of key issues and underlying causes.

Further, it appears that policy level staff were better suited to participate in the Committee's initial emphasis on orientation and visioning appears.

Additional Information:

Back to top.

There needs to be a clear, collective understanding of the roles and responsibilities of participants..

The diverse group of interests participating in TPEAC brought distinct agendas to the table, as should be expected. Particularly for members who did not participate in the latter stages of the committee, this lack of an initial shared agenda presented an obstacle to rapid progress.

Because administrative and budget responsibilities were assigned to WSDOT, concerns were raised regarding WSDOT’s:

  1. Level of control over the proceedings (i.e., agenda setting)
  2. Motives for participating and their influence on the outcomes

Further, the relationship between the full and subcommittees was an area of disagreement.  Some participants felt that the full committee (legislators in particular) should have had a more active role in the subcommittees in order to provide guidance and better understand the processes, issues, and developments of each subcommittee.  Others felt the subcommittees and teams were a place for getting the work done – for permitters and project managers/engineers to talk through the issues. The subcommittees were intended to provide an environment to freely share concerns and collaboratively problem-solve. 

Additional Information:

Back to top.

Effective and appropriate meeting management is critical to ensuring engagement and productivity

The TPEAC experience highlights some of the challenges of bringing together a diverse, statewide group of stakeholders, including:

  • Meeting frequency: The high frequency of initial full committee meetings meant that:
    • Subcommittees often did not have significant progress to report
    • Presenters often did not have adequate preparation time
    • Information distribution did not allow enough time for processing and reflection

  • Participants already full schedules made it difficult to accommodate frequent full committee and subcommittee meetings. Many participants represented their agency on multiple subcommittees. Overlapping subcommittee meeting schedules compromised agency attendance.

  • Facilitation and management resources: Several participants indicated that subcommittees would have benefited from neutral facilitation similar to that used in full committee proceedings.  For some subcommittees, a facilitator was used early in the process, helping with group preparation and providing neutral guidance and advice to the group. As funding for facilitators ended, the responsibility was placed on subcommittee co-chairs. Unless co-chairs had ready access to TPEAC support staff through WSDOT to assist with the meeting management functions, it was a struggle to plan, manage, facilitate, and follow up the meetings. Subcommittee productivity was directly affected by the chair/co-chair’s ability to manage the process.

Additional Information:

Back to top.

Transportation Streamlining Lessons Learned

To get improved project delivery, examine more than just permit decisions.

In TPEAC, initial emphasis was placed on the permitting phase of transportation projects.  Many participants expressed that the TPEAC experience highlighted the need to examine all stages of transportation development for opportunities to reduce conflict and project delay.  For example, the Planning Subcommittee was created to review the planning phase of transportation project delivery in order to promote early identification of environmental issues in preparation for National and State Environmental Policy Act (NEPA and SEPA) review.

Additional Information:

Back to top.

Interagency permit teams can be effective in design, avoiding impact, and compensating impacts of transportation projects.

The approach developed by TPEAC’s One-Stop Permitting Subcommittee involved the use of interagency permit teams comprised of WSDOT, permitting/resource agencies, affected tribes, and private or public sector discipline experts (including engineers).  Teams were developed for two TPEAC Pilot Projects (SR 104 Hood Canal Bridge and SR 24 Yakima Bridge) and the results of their efforts were assessed in a Questionnaire Report. 

Within an interagency team, work on certain items is best relegated to a smaller work group comprised of the most interested parties who can bring their solution back to the larger team. For one of the pilot projects, everyone agreed that the Interdisciplinary Team (IDT) was a major drain on staffing resources for most of the agencies involved.  This was attributed, in part, to meeting topics that could have been addressed in smaller groups (“off-line”). There was general agreement that off-line meetings needed to be used more, better recorded and reported to IDT Team members.  Also, the schedule and demands placed on this permitting process made it difficult for agencies (including WSDOT) to coordinate input and response from technical staff as quickly as was expected.

Additional Information:

Back to top.

Early involvement of transportation and permitting agency staff is key.

For one of the pilot projects, participant comments indicated the Interdisciplinary Team (IDT) should have convened earlier in the project timeline and the pre-application process should have been more thorough.  Early agency involvement in the project well before submittal of applications was considered important and valuable by the resource agencies. One main reason given was that early involvement helps support the correct collection of information and completion of permitting applications.

Additional Information:

Back to top.

Dedicated funding is key.

  • Transportation projects delayed or terminated due to insufficient funds:  Two of the three initial pilot projects faced funding challenges, and one had to be abandoned as a pilot because of insufficient funds.  Inconsistent and/or insufficient funding surfaced not only as an impediment to pilots, but as a major contributor to project delay and inefficiencies.
  • Insufficient funding limited participation by some important players:  At the beginning of TPEAC, participation by some important agencies was missing due to insufficient funding.  The Washington State Department of Ecology and the Washington Department of Fish and Wildlife received TPEAC funding and were able to fully participate.  Other permitting entities (including local agencies, tribes, and federal agencies) had insufficient funding to fully participate and at the same time perform other transportation liaison responsibilities.   

Back to top.

Intra and interagency communication can take more time than expected.

TPEAC required coordination between state and federal agencies, local and tribal governments, and private stakeholder groups.  Communication among and between these entities can take more time than expected but despite challenges, the value of early and consistent communication should not be underestimated. 

Additional Information:

Back to top.

Process improvement requires champions and a willingness to think outside the box.

Streamlining in many ways requires thinking out of the box and a willingness and openness to questioning and challenging established methods and business practices.  Looking to change made during the TPEAC time, a key ingredient concerns the role of the champion or leader who works to keep the process moving and to create an atmosphere or environment that fosters risk-taking.

The experience of the Pilot Project Interdisciplinary Teams and of TPEAC in general involved the integration of permitting processes by agencies with distinct agendas and longstanding approaches.  Concerns were raised that some agencies were unable or unwilling to change their ways of doing business.

Additional Information:

Back to top.

Pilot Project Lessons Learned

Timing parameters and project complexity impact a project’s value as a model or pilot.

When members of one of the pilot projects’ Interdisciplinary Team (IDT) were surveyed, there was general consensus that using a very complex project on a very fast time line provides a less than ideal model or pilot to adequately assess proposed streamlining tools. Use of partially developed streamlining tools was abandoned part way through the process in order to permit the project and deliver it for advertisement by the target date.

Additional Information:

Back to top.

As groups and teams become established, the tendency to form allegiances diminishes.

For one of the pilot projects, some participants were concerned that the IDT forum was a double-edged sword.  On the one hand, efficiencies could be gained by discussing the project and its impacts in a multi-agency forum.  On the other, agencies with similar mandates could also tend to appear allied on an issue initially raised by only one agency. 

Back to top.

Key players must be present at critical times.

Key players were identified as missing during parts of the IPT process. For example one small county reported that they did not participate due to a lack of staff resources, distances to the meetings in Olympia, and a general perspective that the other resource agencies would adequately address the environmental impacts associated with this project. 

Back to top.

Last Updated: March 27, 2006

Acknowledgements | Glossary of Terms | Additional Resources | Comments/Questions  

Access Washington: The Official State Government Website