|
|
Developing and Extending Multi-Agency
Programmatic Agreements
Next Steps
Programmatic approaches can help reduce
permitting time and project costs while protecting
the environment. This also allows staff resources to
focus on more complex projects, and thereby provide
better analysis and response on more challenging
types of projects and permits. Through single sets
of permitting terms, conditions, and requirements
that have been unified and reconciled across
agencies, as well as developed with the input and
perspective of the applicant and affected
stakeholders, the goal of cost-effective,
integrated, protective, and workable regulation can
be achieved. The Transportation Permit Efficiency
and Accountability Committee (TPEAC), the Washington
State Department of Transportation (WSDOT), and others have found
programmatic approaches to be a worthwhile
investment of time and energy [e.g., see (1)
Environmental
Permitting for Transportation Projects Pre-Audit
conducted by the Transportation Performance Audit
Board and (2)
Report on Status of WSDOT Programmatic Permits
issued by WSDOT.]
In looking ahead, TPEAC is pleased to see that the
value and benefits inherent to programmatic
approaches is consistent with those underlying the
Governor’s Regulatory Improvement Program and the
recent
Executive Order #06-02 on Regulatory Improvement.
Accordingly, TPEAC encourages support and leadership
from the Governor’s Office of Regulatory Assistance
(ORA) to further and more broadly apply this
important regulatory improvement approach as
follows:
- Extend Programmatic (and
Multi-Agency Programmatic) Focus More Broadly:
Work begun for WSDOT to develop common
permitting terms and conditions for routine
projects (e.g., WSDOT maintenance work) could be
extended to other routine local and state
transportation, roadway, and infrastructure
projects. The Association of Washington Cities,
the Washington State Association of Counties,
WSDOT, the Regional Road Maintenance Forum
(i.e., group of local and county road
departments that adopted and follow the ESA
approval Regional Road Maintenance Program), and
the state and federal natural resource agencies
should continue to work together to develop
programmatic approaches that address these kinds
of projects and permitted activities. ORA can
play a valuable role in convening these and
other parties to ensure a broader application of
programmatic approaches, e.g., a broader
application of
WSDOT’s existing programmatics.
- Build on Programmatic
Use, Update, and Development Efforts of Others:
Future efforts by the US Army Corps of Engineers to
review and update existing
nationwide permits may provide opportunities for
other agencies to ensure their permitting terms,
conditions, and requirements are appropriately
updated, synchronized, and where possible
integrated. Future efforts by WDFW to update and
develop further programmatics may provide a similar
such opportunity. ORA can play a valuable role in
ensuring regulatory agencies’ comprehensive
awareness of one another’s programmatic use, update,
and development efforts, and encouraging the
synchronization and integration of such.
- Continue Specific Focus on WSDOT:
The
remaining activities for which WSDOT plans to
develop programmatic permits include pile
replacement in fresh water, and seismic retrofit
of bridge structures located over water. WSDOT
expects to begin the development of the pile
replacement permit in Spring 2006 with
completion scheduled for Fall 2006/Winter 2007.
WSDOT expects to begin work on seismic retrofit
in early 2007.
- Measure Performance:
There is a continued need to measure the performance
of programmatic agreements to determine if initial
assumptions on cost/benefit savings and equivalent
resource protection are correct. WSDOT can serve as
a model for the work they’ve done evaluating
cost/benefit savings associated with development and
implementation of programmatic approaches. WSDOT
compiles annual performance data on programmatics
based on frequency of permits used and feedback
regarding utility of the permits from field crews on
an annual basis. As part of the Governor’s
Regulatory Improvement Program, ORA can play a
valuable role in setting an overall framework for
measuring and valuing agencies’ development and use
programmatic approaches.
- Utilize Adaptive Management
Approaches:
TPEAC encourages a
strong commitment to adaptive management when
developing and using programmatic approaches.
Fine-tuning programmatics over time to address
concerns and issues from field staff and applicants,
as well incorporating lessons learned from previous
years’ use, is essential to realizing optimal
cost/benefit and resource protection benefits. ORA
can help to set this expectation as part of the
Governor’s Regulatory Improvement Program.
History/Background Information
TPEAC’s authorizing legislation, ESB 6188,
required the formation of a technical
subcommittee to “. . . create a process to
develop a programmatic approach for
transportation projects.” A “programmatic
approach” is defined as a permit or other action
that:
- covers a geographic or statewide area;
- applies to a variety of projects,
activities, or locales; and
- may allow actions to proceed without
individual approval by each permit
decision-making agency.
The
Programmatic Process Subcommittee
(Subcommittee) began meeting in October 2001 to
develop programmatic approaches that would
expedite project delivery, reduce project cost,
and protect and enhance environmental conditions
through process efficiencies.
Prior to the establishment of TPEAC, the
Washington State Department of Transportation (WSDOT)
had engaged in developing programmatic coverage
for various transportation-related activities by
working directly with individual resource
agencies for certain types or groups of
activities. However, research by the
Subcommittee found that no programmatic approach
had been developed where all jurisdictional
agencies agreed on common conditions for a
specific activity that could lead to project
approval by each agency. Further, in pursuing
programmatic coverage under this process (i.e.,
seeking individual programmatics from each
agency), the Subcommittee identified two
significant issues:
-
Since project conditions were negotiated with
an individual agency, permit conditions often
varied between agencies for each activity; and
- pursuing programmatic coverage under this
process was time consuming due to the complexity
of the issues, lack of dedicated staff and other
resources, and the numerous jurisdictions
involved.
In their April 2002 report to TPEAC, the
Subcommittee:
- summarized their findings on the current
status of programmatic coverage;
- identified and prioritized WSDOT activities
suitable for programmatic coverage; and
- presented their recommended programmatic
approach for approval by TPEAC.
Following TPEAC’s approval of the final report,
the Subcommittee worked to develop programmatic
permits for priority activities. By August 2005,
programmatic agreements had been developed for
all of the transportation activities identified
in the final report with the exception of stream
bank stabilization, bridge scour, and bridge
removal (which were determined to not be
suitable for programmatic coverage because they
are high impact, high risk, site specific, and
non-routine). Currently, programmatic permits
provide coverage for approximately 90% of the
Washington State Department of Transportation's
(WSDOT) Maintenance Program, 30% of WSDOT’s
Preservation Program (e.g., bridge painting and
washing, bridge deck replacement, and pile
replacement), and less than 3% of WSDOT’s
Improvement Program (e.g., culvert replacement
and sediment test boring). The current
programmatic coverage reflects the initial
expectation of the Programmatic Subcommittee
that programmatic permits were suitable for low
impacting activities.
In addition to the efforts of the
Programmatic Permits Subcommittee, TPEAC’s
Local Government Task Force recommended the
development of a nighttime noise programmatic
permit. WSDOT worked with the City of Renton and
the Renton Public Works to develop a
programmatic noise covering nighttime
maintenance work along I-405 within the City of
Renton. This permit was issued in June 2005, and
is valid through October 2010. Once approved,
the permit was immediately utilized for
scheduled maintenance work along I-405. Use of
the programmatic permit will be monitored by
WSDOT to determine how beneficial it is before
applying it in other areas. The programmatic
approach provides predictability in that permit
conditions are set for a period of five years
and will reduce review time by both the City of
Renton and WSDOT.
Ongoing/Related Efforts
The Governor’s Office of Regulatory
Assistance oversees the Governor’s
Regulatory Improvement Program. ORA leads a
multi-agency collaborative program involving
local, state, and federal levels of
government, and works with licensing, tax
collection, permitting, and other regulatory
agencies to improve and simplify regulatory
services, systems, and requirements. In
January 2006, ORA identified further use and
integration of programmatic approaches as a
significant regulatory integration and
improvement opportunity, as well a valuable
way to reduce the complexity of application
and permitting procedures for routine
activities while increasing environmental
outcomes. ORA is now conducting a more
focused Regulatory Improvement Project to
specifically identify and promote
opportunities to develop and use streamlined
programmatic approaches in Washington. Key
to this Project is a comprehensive statewide
survey of environmental programmatic
approaches developed for use in Washington
and the identification of future integration
and alignment opportunities among regulatory
agencies. The intent of the ORA effort is to
realize further gains in regulatory
predictability, use of governmental
regulatory resources, and environmental
outcomes above and beyond those achieved
strictly WSDOT projects.
|
|
|
|